Short answer
Antalya solar plant connection capacity is the power a solar power plant may feed into the distribution grid, as approved in the connection opinion. It is assessed together with the consumption facility's contracted power, the capacity of the transformer at the connection point and whether the site is supplied at low or medium voltage. Exact limits follow current legislation and the Akdeniz EDAŞ connection opinion; confirm them before starting.
Key takeaways
- Installed capacity refers to the power of the modules and inverters, connection capacity to the power that may be fed into the grid, and contracted power to the power in the consumption subscription.
- How these three values limit one another is set by current legislation; exact ratios and thresholds must be confirmed with EPDK and Akdeniz EDAŞ.
- Sites supplied at low voltage depend on the capacity of the local distribution transformer, while medium-voltage subscribers mostly depend on their own transformer.
- Whether an existing transformer suits a solar plant must be checked separately for rating, loading, protection, metering and power factor correction.
- Firm capacity planning done before obtaining the connection opinion increases the risk of project revisions.
In a solar power plant (GES) project, the first question is usually "how many kW can I install?". The answer does not depend only on the size of the roof or the land. Antalya solar plant connection capacity is determined together with grid-side values such as the contracted power of your consumption subscription, the capacity of the transformer you are connected to and whether your site is on low voltage or medium voltage. In this article we simplify these concepts, which are often confused in Antalya solar energy projects, and outline whether an existing transformer is suitable for a solar plant and when a new transformer is needed. We give no exact kW limits or ratios; as of November 2026, these values are set by current legislation and the distribution company's connection opinion.
What is Antalya solar plant connection capacity?
Connection capacity is the power requested in the application for connecting a generation facility to the distribution grid and found acceptable by the distribution company in its connection opinion. In other words, it is the maximum power limit at which the plant can "talk" to the grid. Because the operator of the distribution grid in Antalya is Akdeniz EDAŞ (AEDAŞ), the local distribution company, connection applications and connection opinions are handled through it.
Connection capacity is usually linked to the AC output power of the inverters. The total DC power of the modules (kWp) may differ from it; designing the DC side somewhat larger than the AC side is a common engineering choice. You should therefore pay attention to which value is written as "installed capacity" and which as "connection capacity" in quotations and application documents. We recommend checking the current version of the definitions in the regulations of EPDK, the Turkish energy market regulator.
Installed capacity, connection capacity and contracted power: the difference
These three concepts are used side by side in the same project but describe different things. Contracted power is the power stated in your subscription with the distribution company as a consumer, i.e. the power your site may draw from the grid; it appears on your electricity bill or subscription contract. For unlicensed generation intended for self-consumption, there may be provisions linking the capacity of the generation facility to the contracted power of the consumption facility it is connected to. Since the ratio and conditions of this link can change over time, we do not give an exact value here; it must be confirmed for your project according to current legislation.
| Concept | What it describes | Where you find it | Relevance for a solar plant |
|---|---|---|---|
| Installed capacity (DC, kWp) | Total nameplate power of the modules | Design and equipment list | Basis of the annual yield estimate |
| Installed capacity (AC, kW) | Total output power of the inverters | Inverter datasheet, design | Instantaneous power that can be fed into the grid |
| Connection capacity | Power approved for connection to the grid | Connection opinion, connection agreement | Sets the plant's upper limit |
| Contracted power | Power that may be drawn under the consumption subscription | Subscription contract, bill | May be linked to the capacity of a self-consumption plant |
| Transformer rating (kVA) | Apparent power the transformer can carry | Transformer nameplate, site electrical design | May limit connection capacity |
To calculate how many kW you need from the consumption side, see our article on how many kW of solar panels you need. If the grid-side limit and the consumption-side need give different results, the project takes shape where the two overlap.
LV and MV connection: the general differences
Low voltage (LV) is the grid level that supplies homes, shops and small businesses. These sites are usually fed from a transformer owned by the local distribution company, shared with other subscribers. Medium voltage (MV) is the voltage level of the distribution lines between substations; high-consumption sites such as factories, hotels and large farms often subscribe at MV and own their own transformers.
This distinction directly affects the solar project. At a site supplied at LV, the power at which the plant can connect depends on the condition of the shared transformer and line; other generation facilities connected to the same transformer may already be using the capacity. At an MV-subscribed site, the rating of the business's own transformer, the protection scheme and the metering system become decisive. On the MV side, design, protection coordination and acceptance procedures are generally more extensive. At which voltage level and under which conditions a connection can be made is determined by current legislation and the distribution company's technical assessment.

How does transformer capacity affect connection in Antalya?
In some parts of Antalya where solar investments are concentrated, especially on farmland and rural lines, transformer and line capacity can be the main factor shaping the connection opinion. As the total capacity of generation facilities connected to a transformer grows, there may be no capacity left to connect a new plant at the same point. In that case the distribution company may propose a connection capacity below the requested power, point to a different connection point or state that grid investment is required.
That is why, in Antalya solar energy projects, and particularly for ground-mounted and large rooftop plants, it is important to clarify the connection possibility before placing firm equipment orders. Otherwise the design may need revising to match the approved connection capacity. We explain the general steps of the connection process in our article on rooftop solar applications, and the document issued after the application in our article on the call letter (çağrı mektubu).
Is the existing transformer suitable for a solar plant? A checklist
When a business with its own transformer wants to install a solar plant on its roof or land, it should assess the condition of the existing transformer separately. The transformer may not have been designed for a generation facility; its age, loading and protection scheme may need adapting to the new conditions. The following items are the basic points an electrical engineer will examine:
- Transformer rating and loading: the nameplate rating, the current loading level and the power the plant will add are assessed together.
- Age and maintenance history: oil analysis, insulation measurements and maintenance records indicate whether the transformer is fit for a new operating condition.
- Protection scheme: protection relay settings suitable for reverse power flow and the condition of circuit breakers and disconnectors are checked.
- Metering system: the suitability of the meter and instrument transformers for bidirectional metering is assessed against the distribution company's requirements.
- Power factor correction: once the plant starts covering part of the active power, the ratio of reactive power drawn from the grid may change, so the compensation system and its settings should be reviewed.
- Earthing and switchboard infrastructure: the earthing of the transformer and the main LV board, and the cross-section and protection suitability of the point where the plant will connect, are checked.
During its free site survey, Solar Nexo reviews photographs of the existing electrical infrastructure, nameplate values and the single-line diagram to make a preliminary assessment of the transformer's impact on the project; the final decision is made through the distribution company's connection opinion and the approved design.
When does a new transformer come into the picture?
A new transformer, or an upgrade of the transformer rating, is usually discussed in these situations: the existing transformer is too small for the plant and the consumption, it is old and unsuitable for the new conditions, the site is supplied at LV but the local distribution transformer has no capacity left, or the nearest connection point for a ground-mounted plant requires a separate substation. When a new transformer is required, and by whom and to what standard it will be installed, is stated in the connection opinion and the connection agreement.
A new transformer extends the project's timeline and scope. Approval of the transformer design, manufacturing and delivery times and acceptance procedures form a timeline separate from the plant installation. The possibility of needing a transformer should therefore be built into the scenario from the very start of investment planning. You can find the general framework for large roofs in our article on solar plants for organised industrial zone (OSB) and factory roofs.

Getting information from Akdeniz EDAŞ: the route for a solar power plant application in Antalya
The most reliable source of information on Antalya solar plant connection capacity is the distribution company the application will be filed with. Once the project idea is clear, the following steps can be followed:
- Collect the consumption facility's subscriber details, contracted power and the last 12 months of consumption data.
- Determine whether the site is supplied at LV or MV and, if it has its own transformer, its nameplate values.
- Calculate the intended DC and AC power at preliminary design level.
- Confirm the application conditions and required documents with Akdeniz EDAŞ and the current EPDK regulations.
- File the application and wait for the connection opinion; finalise the design according to the approved connection capacity.
For net metering (mahsuplaşma) applications this process can take 8–12 months on average; Solar Nexo's contracted installation delivery time of 14 working days is independent of it. To see the whole process from application to acceptance, take a look at our Antalya solar power plant guide.
The planning errors we frequently encounter in the field paint a similar picture: deciding the number of modules without checking the contracted power, mixing up DC and AC power in documents, requesting a quotation for a high-capacity system without knowing the transformer's nameplate rating, and ordering equipment before the connection opinion arrives. What these errors have in common is that the question of Antalya solar plant connection capacity must be addressed at the start of the project, not at the end. Having your subscription documents and switchboard photographs ready for the survey speeds up the assessment.
Conclusion
Antalya solar plant connection capacity is determined more by the conditions of the grid and the subscription than by the size of the roof or land. Distinguishing between installed capacity, connection capacity, contracted power and transformer capacity is the first step towards realistic project planning. For sites supplied at LV, the capacity of the local transformer is decisive; for MV subscribers, it is the rating, protection, metering and power factor correction of the business's own transformer. Since exact limits are set by current legislation and the Akdeniz EDAŞ connection opinion, confirming this information before ordering equipment protects an investment in solar energy in Antalya from the risk of revisions. Solar Nexo carries out this preliminary assessment with you during its free site survey.
Frequently asked questions
Are connection capacity and installed capacity the same thing?
No, they are not the same. Installed capacity refers to the total DC power of the modules or the AC output power of the inverters. Connection capacity is the power the distribution company approves in its connection opinion, i.e. the power the plant may feed into the grid. Because designing the DC side slightly larger than the AC side is common, these values can differ; check which one is written in the documents.
Does my contracted power limit the installed capacity of my solar plant?
For unlicensed generation intended for self-consumption, it can. Current legislation may contain provisions linking the capacity of the generation facility to the contracted power of the consumption facility it is connected to. Since the ratio and conditions of this link can change over time, you need to confirm the exact value as of November 2026, according to current legislation, with EPDK regulations and Akdeniz EDAŞ.
What is the main difference between an LV and an MV connection?
The main difference is the voltage level at which the site is connected to the grid. Sites supplied at LV are usually fed from a shared transformer owned by the distribution company, and the power that can be connected depends on that transformer's capacity. MV subscribers mostly own their transformers; in that case the business's transformer, protection scheme and metering system are decisive.
What happens if the local transformer has no capacity left?
The distribution company may propose a connection capacity below the requested power, point to a different connection point or state that grid investment is required. That is why it is important, especially for ground-mounted and large rooftop plants, to obtain the connection opinion before placing firm equipment orders. Otherwise the design may need to be revised to match the approved power.
How do I know whether my existing transformer is adequate for a solar plant?
This needs to be assessed by an electrical engineer. The transformer's nameplate rating, current loading, age and maintenance history, protection relay settings, metering system, power factor correction and earthing are examined together. Solar Nexo includes this information in a preliminary assessment during its free site survey; the final decision is made through the distribution company's connection opinion and the approved design.
Why is power factor correction affected when a solar plant is installed?
When the plant starts covering part of the site's active power demand, the active power drawn from the grid falls, but the reactive power demand may stay the same. This can change the reactive power ratios. It is therefore recommended, especially for MV-subscribed businesses, that an engineer reviews the compensation system and its settings before the solar plant is commissioned.
Where can I get definitive information on connection capacity?
Definitive information comes from the distribution company the application is filed with, which in Antalya is Akdeniz EDAŞ. EPDK regulations should also be followed for application conditions and definitions. If subscriber details, contracted power, the last 12 months of consumption and any transformer nameplate values are prepared before applying, the process runs more smoothly. The design is finalised according to the approved connection capacity.